[3] The 2nd Niger Bridge Will Cost about N117 billion.

[4] Started in 2013 and should have been completed in 2017, but worked stopped for 31 months. Completion date Not certain now.

[5] FGN share of the Cost is N30billion. Jonathan through the Sure-P paid N21.2billion (71%) including N7billion for the completion of preparatory work (Phase 1).

[6] 38% of the work has been done as at Jan 2015.
[7] The N140b Oshiomhole said was wasted on Admin cost on the bridge was a lie, as admin cost will not be higher the to cost of the whole project.

[8] Buhari’s Govt Paid N2billion NOT $2billion as Osinbajo said during the Anambra state election. They will be paying another N3.05 when 2018 budget is approved.

[9] Work has restarted in earnest at the site and about 5%-7% has been completed bring the total completed work to about 43% to 45% according to an engineer I spoke to.

[10] All the pictures flying all over the internet are pictures of work-in-progress made during the 1st quarter of 2015.